Abbot Point Bund 1 Rail Replacement
At Abbot Point TEAM Group (Aust) removed and replaced the stacker reclaimer rails on bund 1 that had
exceeded its design life due to age and corrosion
Our work covered:
-
removal of old rails
-
removal of Pandrol clips
-
transportation of 60m long sections of rail and position on bund
-
installation and welding of the rail
-
performing NDT on welds
-
alignment of the rail and survey to confirm alignment
-
grouting of sole plates
-
moving SR to new rail section and repeat steps to replace balance of rail.